Before You Buy

  • Define essential vs whole-home loads
  • Perform load calculation
  • Confirm fuel type
  • Check natural-gas meter or propane capacity
  • Choose generator size
  • Choose transfer-switch strategy
  • Decide whether load management is needed

Site Selection

Pad / Base

  • Confirm approved base type
  • Level site
  • Confirm drainage
  • Confirm anchoring requirements
  • Confirm wind/flood requirements

Read generator pad requirements →

Electrical

  • Confirm service amperage
  • Confirm panel/service condition
  • Select correct ATS
  • Size generator conductors
  • Confirm disconnect/breaker
  • Confirm grounding/bonding
  • Install control wiring
  • Confirm utility sensing
  • Confirm battery-charger circuit

Read generator electrical requirements →

Fuel

Natural Gas

  • Confirm generator full-load demand
  • Confirm meter capacity
  • Confirm regulator capacity
  • Size gas pipe
  • Confirm shutoff
  • Pressure-test as required

Propane

  • Confirm tank size
  • Confirm vaporization capacity
  • Confirm regulator
  • Confirm line sizing
  • Confirm initial fill

Read generator gas-line requirements →

Permits

  • Electrical permit
  • Gas/plumbing permit if required
  • Mechanical/building permit if required
  • HOA approval if required
  • Utility approval if required

Read generator permits →

Installation Day

  • Generator placed level
  • ATS installed
  • Electrical connected
  • Fuel connected
  • Battery installed
  • Controller configured
  • Generator in AUTO
  • Exercise schedule configured

Commissioning

  • Generator starts
  • No active alarms
  • Simulated outage performed
  • ATS transfers to generator
  • House receives power
  • Major loads tested
  • Load management verified
  • Utility restoration tested
  • ATS transfers back
  • Generator cools down and stops

Inspection / Handover

  • Final inspections passed
  • Permits closed
  • Model/serial documented
  • Warranty registered if applicable
  • Maintenance schedule explained
  • Dealer/service contact saved
  • Owner understands AUTO/OFF
  • Owner knows generator breaker location

Quote Checklist

Before signing, confirm the quote includes:

  • Generator
  • Transfer switch
  • Pad
  • Electrical work
  • Fuel work
  • Trenching
  • Permits
  • Load management
  • Startup/testing
  • Cleanup
  • Warranty/registration

Bottom Line

A standby installation is complete only when the entire system works:

fuel + engine + electrical + transfer + house load + automatic operation

Do not accept "the generator starts" as final commissioning.

Read generator installation process →